Connection of power plants to the power grids.
Here you will find information about the entire joining process, necessary steps and documents.
|
|
|
0700 10 010 info@cezelectro.bg |
0700 1 7777 info@evn.bg |
0700 161 61 info@erpsever.bg |
|
Request for a study to join the ERP
|
|
- Proof of ownership;
- Sketch of the property;
- Photovoltaic power plant design visa;
- Conceptual design;
- Declaration under Art. 24, para. 1 of ZEVI;
- Power of attorney;
|
|
Issuance of an opinion on accession by the EPR
|
|
Request for the conclusion of a Preliminary Contract for joining the ERP for power plants over 30KW
|
|
- Photovoltaic power plant design visa copy;
- Copy of an opinion from the EPR;
- Power of attorney;
|
|
Issuance of a Preliminary Contract for Accession by the ERP
|
|
Submission of projects for the electrical part for approval by the ERP for power plants over 30KW
|
|
- A copy of the Preliminary Agreement for Accession with the ERP;
- Work projects part electrical;
- Power of attorney;
|
|
Coordination of projects of the electrical part of the ERP
|
|
Submission of a request to the relevant Municipality for the issuance of a permit for the construction of a photovoltaic power plant
|
|
- Proof of ownership;
- A copy of the Preliminary Accession Agreement with the ERP;
- Work projects part electrical;
- Photovoltaic power plant design visa;
- Constructive opinion;
- Power of attorney;
|
|
Issuance of a permit for the construction of a photovoltaic power plant by the relevant Municipality
|
|
Request for the conclusion of a Final Contract for joining the ERP for power plants up to and over 30KW
|
|
- Proof of ownership;
- A copy of the Preliminary Agreement (statuše) for joining with the ERP;
- Work projects part electrical;
- Constructive opinion;
- Permit for the construction of a photovoltaic power plant;
- Power of attorney;
|
|
Conclusion of a Final Contract for joining the ERP for plants up to and over 30KW
|
|
Submission of Projects for the electrical part for the coordination of connection facilities from the ERP for power plants up to and over 30KW
|
|
- Copy of the Final Accession Agreement with the ERP;
- Work projects part electrical;
- Constructive opinion;
- Power of attorney;
|
|
Coordination of projects of the electrical part of connection facilities from the ERP for power plants up to and over 30KW
|
|
Submission of a request to conduct 72-hour complex tests of the site and the connection facilities to the ERP
|
|
- Copy of the Final Accession Agreement with the ERP;
- Contract for the supply and installation of a photovoltaic plant and connecting equipment;
- Permit for the construction of a photovoltaic power plant;
- Agreed projects of some electrical connection facilities, agreed by the ERP;
- Declaration of conformity and quality certificates for all materials put into the object;
- Certificate of control and Protocols of control of resistance of grounding and lightning protection grounding installations of Photovoltaic power plant, newly built connection facilities and insulation of newly laid CEL;
|
|
Completion of conducting 72-hour complex tests of the site and of the connecting facilities to the ERP
|
|
Request to enter into an EPP Access Agreement for plants up to and over 30KW
|
|
- A list of persons from the operational and repair staff of the power plant, with the relevant safety group, responsible for the facilities, as well as telephones or other means of 24-hour communication;
- Constitutive protocol for installed commercial measuring device for the conducted 72-hour complex tests of the connecting equipment - copy;
- Power of attorney;
|
|
Conclusion of an Access Agreement with ERP for plants up to and over 30KW
|
|
Request to enter into an Agreement for the purchase of the produced electricity to a selected trader
|
|
- Proof of ownership;
- Accession Agreement;
- Access Agreement;
- Power of attorney;
|
|
Conclusion of an Agreement for the purchase of the produced electricity with a selected trader
|
|
Request to energize connection facilities
|
|
- Declaration of compliance of the electrical equipment of the power plant with the requirements of safety norms and technical norms;
- Declaration of availability of trained operating personnel, operating instructions, operating diagrams and technical documentation necessary for normal operation;
- Executive readings, test reports, characteristics and equipment setup agreed with ERP;
- Contract for the access of an electric power producer to the electricity distribution network of ERP;
- A list of persons from the operational and repair staff of the power plant, with the relevant safety group, responsible for the facilities, as well as telephones or other means of 24-hour communication;
- A copy of the concluded contract for the purchase of the produced electricity;
- Power of attorney;
|
|
Conclusion of an Agreement for the purchase of the produced electricity with a selected trader
|